Progress
Funding, milestones, and the build.
Where things stand
Planning comes first.
The project is in its early planning stage. Fundraising will open once a U.S. nonprofit is in place to receive gifts and keep the records. Until then, we are not accepting donations.
$207,220
Estimated project budget · 9 line items
- Land
- Purchased by Pastor Nelson
- Campus plan & budget
- Drafted
- U.S. nonprofit partner
- Not yet in place
- Fundraising
- Not yet open
The full campus plan. When fundraising opens, this drawing will fill in with color as support comes in.
Milestones
The build journey.
Land
Purchased (complete)
Planning
In progress (current)
Fundraising
Opens with a U.S. nonprofit
Groundwork
Upcoming
Foundations
Upcoming
Classrooms
Upcoming
Water + Solar
Upcoming
Campus Complete
Upcoming
Accountability
Every dollar has a destination.
When fundraising opens, gifts will first be received by a U.S. nonprofit responsible for accounting and record keeping before approved project funds are transferred to Uganda for groundwork, materials, and campus development. That nonprofit is not yet in place, so no donations are being accepted today.
- Step 1
Your gift
Given online or by check.
- Step 2
Receiving nonprofit
Responsible for accounting and record keeping.
- Step 3
Approved transfers
Project funds sent to Uganda.
- Step 4
The build
Groundwork, materials, and campus development.
| Item | Cost |
|---|---|
| Administration | $29,250 |
| Classroom block 1 · Nursery / Pre-K | $40,300 |
| Classroom block 2 · P1–P3 | $40,300 |
| Classroom block 3 · P4–P7 | $40,300 |
| Kitchen | $12,480 |
| Water collection | $14,300 |
| Solar power | $20,800 |
| Grounds & gardens | $3,250 |
| VIP latrines | $6,240 |
| Total | $207,220 |
| Total received | — |
|---|---|
| Transferred to project | — |
| Construction spend | — |
| Remaining funds | — |